1. Introduction
The meeting was chaired by Bruno Schmitz (BS) who welcomed the Team members and
especially Myrsini Christou, the Greek Team member who attends the EIBI Team Meeting
for the first time, Borja Izquierdo who accompanied the Spanish member and Vanessa Marmy
who replaced for this meeting the Swiss Team member.
BS announced to the Team that the EBTP has nominated Carmen Millan (Abengoa, Spain) to
be an industrial representative in the Team, replacing Valentín Ruiz Santa Quiteria (Repsol,
Spain). Valentín Ruiz Santa Quiteria will remain available as substitute of EBTP industrial
representatives.
The minutes of the 8th EIBI Team meeting held on 25 April 2012 were adopted.
2. Outcome of the EIBI Conference held on 5 June 2012
Maria Velkova (EC) represented the outcomes and conclusions of the EIBI Conference held
in Brussels on 5 June and proposed some follow-up actions. Her presentation is attached to
these minutes. All the presentations and the video are available online
(http://ec.europa.eu/research/index.cfm?pg=conferences&eventcode=2D304246-F139-B469-7B52295CAA70E6CB).
The content and format of the next edition were discussed and it was agreed:
• To propose a more focused agenda around 1-2 issues: these issues should be highly
relevant to attract industry and high profile participants,
• To plan more time for discussions (roundtable and long coffee breaks),
• To involve more the EIBI Team members in the organisation from the start (e.g. on
the definition of the agenda): the German and the Spanish representatives volunteered
to coordinate MS views and to contribute to the proposal for the next edition; the
EBTP will coordinate the input from industry,
• That the EC will continue to provide support for the logistics,
• To set a date for the next conference by October 2012,
• To organise the next edition in Brussels.
3. Bio-based industries Public Private Partnership (PPP): possible partial integration of
EIBI activities into this PPP
1
- Update timetable for the preparation phase
Virginie Rimbert (EC) updated the Team members on the timetable for the preparation of the
proposed bio-based industries PPP. DG RTD-Directorate E (Food, Agriculture and
Biotechnology) is currently leading the preparation of a possible JTI on Bio-based industries.
So far, the industry prepared a Vision Document entitled "Bio-based for Growth" (the latest
version is attached to these minutes), and a draft letter of commitment of the founding
members with a commitment of 2.8 bn euros.
In the proposed timetable it is foreseen to present the Council Regulation to the College of
Commissioners in the first quarter 2013. This will imply that the Impact Assessment is
completed by mid-October 2012, and a Joint Vision Statement by the end of 2012. The Joint
Vision Statement will be prepared by the Commission services together with the industry, and
will notably describe the objectives, implementation modalities and monitoring mechanisms
of the PPP.
It was reminded that the type of instrument to be used (contractual PPP or JTI) is still not
decided. Should the JTI option be preferred, an alternative timetable is to wait for the second
wave of JTI proposals, after a first wave devoted to the extension / revision of the current
JTIs.
- Position of the EIBI industrial members on the level of integration of EIBI activities into
the proposed PPP
Lars Hansen (Chairman of the EBTP Steering Committee, Novozymes) presented the analysis
prepared by the industrial members of the EIBI Team regarding the possible integration of
some EIBI activities into the proposed bio-based PPP.
The Vision Document and the position of the industrial EIBI members were discussed. Some
EIBI Team members expressed their concerns that Energy may not be sufficiently considered
in the vision paper in relation to other biomass uses, and suggested that the Vision Document
should be revisited.
BS explained that the Vision Document reflects the vision of industry at this point in time,
and is not endorsed by the Commission. It will be one of the elements used to prepare the
Joint Vision Statement, but not the only one.
After the discussion, it was agreed that:
• MS representatives will send their comments to the EC on the Bio-based industry
Vision Document, and on the position of the industrial EIBI members regarding the
possible integration of some EIBI activities into the proposed PPP, by 16 July,
• The EIBI Team position will be revised accordingly and recirculated to all EIBI Team
members.
• This will be used as an input to the Working Group in charge of preparing the Joint
Vision Statement that will present the common vision of EC and industry regarding
the content of the bio-based PPP.
2
[NOTE 1: the position paper drafted by the industrial members of the EIBI Team was sent to
all EIBI Team members on 3 July. The last version of the industry Vision Document is
attached to these minutes].
[NOTE 2: DG RTD-Directorate E (KBBE) did not circulate the Vision Document to the MS
as it is a document endorsed by industry only. The document is not published yet. No revision
of this document is planned].
[NOTE 3: A bilateral meeting between DG RTD and DG ENER is planned for next
17 September on this subject].
4. Implementation of the EIBI core activities: ongoing activities
- ERA-NET+ 2012: Update on the negotiations
Chris Dowle (UK) presented the status of the negotiations of the BESTF proposal. His
presentation is attached to these minutes. The outcome of the negotiations will be
communicated to the Team as soon as possible.
- "Biofuels FlightPath": update
Recently 2 workshops have been organised, devoted to:
1.
Upstream R&D and Innovation for Paraffinic Biofuels - During the Biomass Conference
& Exhibition in Milan on 18/06. Stakeholders discussed new value chains and conversion
process to paraffinic biofuels that are still in early development stage. This includes
thermochemical pathways (synthetic biofuels, pyrolysis and catalytic conversion of
alcohols) and microbial pathways. Important advances and new technologies in this field
were presented. The presentations given during the Workshop can be found at:
http://ec.europa.eu/energy/technology/events/2012_06_18_biofuels_flightpath_en.htm
2.
Incentives - During the Sustainable Energy Week in Brussels on 20/06, the various
incentives that could facilitate and accelerate the market deployment of advanced
paraffinic sustainable biofuels in the aviation sector were discussed. The main outcome
was that there is no need for a specific mandate within the RED. The presentations given
during the Workshop can be found at:
http://ec.europa.eu/energy/technology/events/2012_06_20_biofuels_flightpath_en.htm.
There will be no new workshop before spring 2013, the priority being now to analyse and
draw conclusions from the various meetings organised in the 1st year of the Initiative.
Summaries of the presentations given during the last 3 workshops will be prepared and
uploaded on the Europa site.
Beginning of October there may be a meeting with major oil companies. There may also be a
revision of the Initiative Roadmap by November 2012.
The Biojet Map project is an information and dissemination tool for biofuels use in aviation.
It is progressing well, with a test version already in operation. A new template is under
3
discussion to collect information on projects. The tool is expected to be available for the
general public by the end of 2012.
A tender studying the use of biofuels in aviation in blends in the range of 50 to 100% has been
issued. Proposals are expected by 27 July.
The topic of DG ENER in the 2013 Energy Call focuses on demonstration-scale plants for the
production of paraffinic biofuels for use in aviation.
5. Implementation of the EIBI core activities: future activities
- New ERA-NET+ topic for demonstration projects in WP2013
The topic will be published next 10 July. The EC budget for this topic is 20 M €.
The following MS expressed interest in this topic: DE, GR, NL, ES, UK, while indicating that
it is too early to know whether a budget can be committed.
- Working Group on end-uses
Franco Cotana (IT) presented ideas regarding the scope of the WG on end-uses. His
presentation is attached to these minutes.
After discussion, it was proposed to narrow the scope of this WG to 2 topics (road transport
and maritime sector), but it will start working on the maritime sector as a test case.
- Working Group on the financing of bioenergy flagship projects
This point was removed from the agenda. The Working Group should meet in the coming
months and a state of play will be given at the next EIBI Team meeting.
6. Next meeting The 10th EIBI Team meeting is scheduled on 10 October 2012 in Brussels
7. AOB
Kees Kwant (NL) communicated the outcome of his consultation with the bioenergy research
community, notably the EERA bioenergy group, regarding infrastructures. The conclusion is
that there is a need to support research infrastructures for biochemical technologies in
bioenergy.
[NOTE 4: Kees Kwant will prepare a document in coordination with EERA explaining and
justifying the needs identified. This document will be provided as an input from the EIBI
Team to the services in charge of the infrastructures programme].
- Workshops on longer-term R&D
4
An email was sent to EIBI Team members on 18 June, informing that the two workshops on
longer-term bioenergy research (initially scheduled back-to-back with the 9th EIBI Team
meeting) had been postponed to 3 and 4 September. In this same email, EIBI Team members
were recalled to provide names of potential participants and speakers for the workshops
directly to Francisco Gírio, representative of EERA and of Portugal in the EIBI Team.
According to the feedback provided by Mr Gírio (not present at the meeting), the response
received to date has been very limited, and the list of participants and speakers is not
finalised. Given the difficulties to contact potential participants during the summer holidays, it
was decided to again push the workshops to October or November. A new date will be
proposed shortly.
EIBI Team members were requested again to provide names of potential participants to
Francisco Gírio, within the shortest possible delay. To better understand the aims of the
workshops and facilitate the choice of potential participants, the presentation made by
Mr Gírio at the EIBI conference of 5 June is annexed to these minutes.
ACTION POINTS
Actions for Industry / MS
• EIBI Team members to provide names of potential speakers and participants to the
workshops on longer-term R&D needs as soon as possible. Names to be sent to
xxxxxxxxx.xxxxx@xxxx.xx, with xxxx.xxxxxxxxx@xx.xxxxxx.xx and vicky.van-
xxxxxx@xx.xxxxxx.xx in copy.
• MS to comment on the Vision Document and on the document indicating the position
of the EIBI industrial members regarding the possible links between the EIBI
activities and the bio-based PPP by
15 July 2012. Comments to be sent to
xxxxxxxx.xxxxxxx@xx.xxxxxx.xx and xxxx.xxxxxxxxx@xx.xxxxxx.xx
Actions for EC
• The EC to communicate the outcome of the ERA-NET+ negotiations to the Team
members as soon as possible.
5
•
List of participants:
Representatives of MS/AC
Bunger Jan, DEA, Denmark, xxx@xxx.xx
Cooper Megan, DECC, UK, xxxxx.xxxxxx@xxxx.xxx.xxx.xx
Cotana Franco, CRB, Italy, xxxxxx@xxxxxx.xx
Christou Myrsini, CRES, Greece, xxxxxxx@xxxx.xx
Dowle Chris, CPI, UK, xxxxx.xxxxx@xxxxxx.xxx
Fernández Lopez Carlos Alberto, IDEA, Spain, xxxxxxxxx@xxxx.xx
Izquierdo Borja Alonso, CDTI, Spain, xxxxx.xxxxxxxxx@xxxx.xx
Johansson Sebastian, TEKES, Finland, xxxxxxxxx.xxxxxxxxx@xxxxx.xx
Kerckow Birger, FNR, Germany, x.xxxxxxx@xxx.xx
Kwant Kees, Agency-Energy and Climate Change,Netherlands, xxxx.xxxxx@xxxxxxxxxxxx.xx
Marmy Vanessa, Swiss Mission to the EU, Switzerland, xxxxxxx.xxxxx@xxx.xxxxx.xx
Vural Asli, TUBITAK, Turkey, xxxx.xxxxx@xxxxxxx.xxx.xx
Representatives of Industry
Degano Cristina, M&G Chemtex, Italy, xxxxxxxx.xxxxxx@xxxxxxxx.xxx
Hansen Lars
, Novozymes, Denmark, xxxx@xxxxxxxxx.xxx
Karlsson Markku, UPM (EBTP), Finland, xxxxxx.xxxxxxxx@xxx.xxxxxxx.xxx
Lindman Eva-Katrin, Fortum, Sweden, xxxxxxxxxx.xxxxxxx@xxxxxx.xxx
Millan Carmen, Abengoa (EBTP), Spain, xxxxxx.xxxxxx@xxxxxxxxx.xxxxxxx.xxx
Ruiz Santa Quitéria Valentin, Repsol, xxxxxx@xxxxxx.xxx
EC representatives
Georgiadou Maria, RTD-K3, xxxxx.xxxxxxxxxx@xx.xxxxxx.xx
Rimbert Virginie, RTD-K3, xxxxxxxx.xxxxxxx@xx.xxxxxx.xx
Maniatis Kyriakos, ENER-C2, xxxxxxxx.xxxxxxxx@xx.xxxxxx.xx
Ruiz Espi José, RTD-K3, xxxx.xxxxxxxxx@xx.xxxxxx.xx
Schmitz Bruno, RTD-K3, chair of the EIBI Team, xxxxx.xxxxxxx@xx.xxxxxx.xx
Van Delsen Vicky, RTD-K3, xxxxx.xxxxxxxxxx@xx.xxxxxx.xx
Velkova Maria, RTD-K3, xxxxx.xxxxxxx@xx.xxxxxx.xx
6