Ref. Ares(2016)2419062 - 25/05/2016
Draft calendar for the cloning impact assessment (Proposal for 2013-CWP)
Timing Actions
Phase I (2 months)
-First Steering group meeting.
SANCO Policy strategy
-Draft Roadmap.
Roadmap
-Request for update of the EFSA statement.
November-December 2011
-Signature of contract with consultant.
Phase II (7 months)
Public consultation:
Consultation and analysis
-Steering Group meetings. (4-5).
I
Impact Assessment exercise
-Advisory group meetings (2-3).
S
January-July 2012
S
FEBRUARY -Questionnaire to the Member States and third
G
countries.
-Inception report of consultant.
M
MARCH -Interactive Policy Marketing tool (IPM internet
E
based) Open for 12 weeks.
E
-Interim report of consultant.
T
JUNE -Final Report of the consultant.
I
-New EFSA statement.
N
G
JULY -Drafting of the IA report.
S
Phase III (4 months)
SEPTEMBER -Submission of the IA report to the Board.
OCTOBER-NOVEMBER -Adoption of the IA report by the Board.
-If Adoption of the IA report, drafting of the
proposal (1month).
DECEMBER -Draft proposal finalised.
-INTRA SANCO + CAB approval.
Phase IV (3 months)
Commission policy output
-CIS of IA report and executive summary +Opinion
Adoption
of the board + proposal.
-Translation finalised.
MARCH -Adoption by the Commission.
-Transmission to other institutions.
Version 27/01/2012