Ref. Ares(2016)2419062 - 25/05/2016
Draft calendar for the cloning impact assessment (Proposal for 2013-CWP) 
 
 
Timing Actions 
Phase I (2 months) 
-First Steering group meeting.  
 
SANCO Policy  strategy 
-Draft Roadmap. 
 
Roadmap 
-Request for update of the EFSA statement. 
 
November-December 2011 
-Signature of contract with consultant.  
 
 
Phase II (7 months) 
Public consultation: 
 
Consultation and analysis 
-Steering Group meetings. (4-5). 

Impact Assessment exercise 
-Advisory group meetings (2-3).  

January-July 2012 
 

FEBRUARY  -Questionnaire to the Member States and third 

  countries. 
 
  -Inception report of consultant. 

MARCH   -Interactive Policy Marketing tool (IPM internet 

                                                   based) Open for 12 weeks. 

  -Interim report of consultant.  

JUNE  -Final Report of the consultant. 

 
-New EFSA statement. 

                                  
 

JULY  -Drafting of the IA report. 

 
Phase III (4 months) 
 
SEPTEMBER  -Submission of the IA report to the Board.  
OCTOBER-NOVEMBER  -Adoption of the IA report by the Board.  
  -If Adoption of the IA report, drafting of the 
  proposal (1month). 
DECEMBER  -Draft proposal finalised. 
-INTRA SANCO + CAB approval. 
 
Phase IV (3 months) 
 
Commission policy output 
-CIS of IA report and executive summary +Opinion 
Adoption            
of the board + proposal. 
  -Translation finalised. 
MARCH  -Adoption by the Commission. 
-Transmission to other institutions. 
 
 
Version 27/01/2012