 was identified in the completion of sprint 5, Everis explained that this delay 
was due to the different demos and other unforeseen activities, and should not jeopardize 
the overall timelines for this iteration (iteration 4) nor for the delivery of the project. On the 
other hand, Everis has made good progress on the preUAT 7 bug fixing (6 bugs closed) 
 

 (after the merge of R0.7 and R0.9) identified   new bugs (59 previously 
unidentified bugs existing in R0.7) on top of the 
 existing bugs 
 

 
Outcome:  Group  members  are  invited  to  submit  additional  comments  on  the  KPIs  by  eob 
Wednesday (April 24) directly to EMA (keeping the rest of the team in the loop of communication).
EMA on the basis of the comments from today will already update the draft on KPIs so that this new 
version can be discussed at the next monitoring meeting on May 2. Commission suggested to take 
into account those KPIs that are currently used for internal progress reports. 
 also proposed to 
draft  by  April  30  a  high-level  paper  to  assess  the  expectations  vis  a  vis  Everis  in  6  months  as 
requested by the coordination group. EMA will send exact deliverables of the contract. The  Group 
members and EMA agreed to provide assistance with this work.  
 
 
 
 