detailed information on possible duration of the later plant commissioning stages. 
Nevertheless, to estimate the durations of the individual commissioning activities,  the real dates 
of  major  commissioning  milestones  of  other  recently  completed  VVER  NPPs  have  been 
compared  to  the  planned  dates  for  BelNPP  in  the  Table  2.  The  relatively  short  intervals 
between  the first  criticality and  the first grid  connection  at  Tianwan 2,  Kalinin 4  and  Rostov  3 
may  indicate  either  a  reduced  scope  of  start-up  test  usual  at  the VVER-reactors  or  a  quick 
power  increase to  a  level  eligible  for  a  grid  connection  and  subsequent return to  zero  power 
level tests. 
As  an  example  of  actual  VVER  plant  commissioning  activities,  a  detailed  list  of  tests  as 
performed  in  the  zero-power  and  power-ascension  stage  of  the 
- commissioning  has  been  provided  in  the  Annex  4.  It  should  be  noted  that  most
stages of the  power  ascension  test  period  included  periods of  reactor  hot  or  cold  shutdowns
Art. 4(2) first indent 
{into modes 3-6) to perform plant s  stem inspections, revisions or eliminate problems.
In any case,  the actual  duration of the commissioning  period at the BelNPP will depend on the 
actual  composition  of  the  commissioning  programme  and  number  of  parameters  tested.  In 
general,  the commissioning phase can be expected to be longer at the BelNPP 1 being kind of 
a pilot one. 
A direct comparison of the commissioning milestones has been performed in the Table 2 below: 
Table 2 
Plant 
Fuel 
First 
Connection  to  the  Commercial 
loaded 
criticality 
grid 
Operation 
Be/NPP 1 
April 2018 
May 2018  (+1 m) 
Dec 2018  (+ 8 m) 
Novovoronezh  11/1 
04/04/2016  20/05/2016  June  2016 
(+1 
m)[26) 
Leningrad 1111 
End 
of  May2017 
January 2018 
2016") 
Art.4(2) first indent 
Tianwan-1 
Dec 2005 
May 2006 (+ 5 m) 
May 2007 {+ 17 m) 
Tainwan-2 
May 2007 
May  2007  {+  2  Aug 2007 (+ 3 m)
weeks) 
Kalinin-4 
Nov 2011 
Nov  2011  (+  2  Dec 2012 (+ 14 m) 
weeks) 
Kudankulam-1 
July 2013 
Oct 2013  (+ 3 m) 
Dec 2014 (+ 17 m) 
Rostov 
Dec 2014 
Dec  2014  (+  3  Sept  2015  (+  10 
(Volgodonsk)-3 
weeks) 
m) 
planned dates 
Page 8 of 17 


















MGR equipment installation started 
15.1.2016 
LNNP  11/1  will  start  commercial  operation  In  January  2018  29.1.12016 
because of lower power demand 
Main condensers mounted to the LP turbines 
4.3.2016 
Reactor building construction finishes 
14.3.2016 
Dieselgenerators (made in  Finland) delivered on-site 
18.3.2016 
Refuelling machine installed in the containment 
20.3.2016 
Construction  workers  on  LNPP  II  site  worried  about  low  23.3.2016 
wages and refuse to work 
Flushing of the main steam line started 
15.4.2016 
Filters of continuous primary coolant treatment system installed 
18.4.2016 
Installation of the  containment pre-stressing system 
27.4.2016 
Cementing  of the external containment  dome finished 
18.5.2016 
Annex4 
Art.4(2)(first indent  Main stages of 
commission programme [23][25] 