Esta es la versión HTML de un fichero adjunto a una solicitud de acceso a la información 'EIB loan agreements and EIT InnoEnergy agreements for raw materials'.


 
 
 
 
Contract Number […] 
 
Operation Number (Serapis N°) 2019-0611 
EIB Internal Classification Level: Corporate Use 
 
 
 
 
UMICORE EUROPEAN LARGE-SCALE BATTERY 
MATERIALS  
Finance Contract 
between the  
  European Investment Bank   
and 
 
Umicore  
 
 
 
Brussels, 10 June 2020 
Luxemburg, 10 June 2020 
 
 
 

 
 
[…] 
 
THIS CONTRACT IS MADE BETWEEN:  
The  European  Investment  Bank  having  its   
(the "Bank") 
seat  at  100  blvd  Konrad  Adenauer, 
Luxembourg, 
L-2950 
Luxembourg, 
represented by […] 
of the first part, and 
 
 
 
Umicore,  a  public  limited  liability  company   
(the "Borrower") 
(naamloze vennootschap / société anonyme
incorporated  and  existing  under  the  laws  of 
Belgium,  having  its  registered  office  at 
Broekstraat 31 rue du Marais, 1000 Brussels, 
Belgium,  registered  with the  register  of  legal 
persons under number RPR/RPM (Brussels) 
401.574.852, represented by […]   
of the second part. 
 
 
 
 
 
 
 
 

 
 

 
 
WHEREAS: 
[…] 
(h) 
The Bank considers that access to information plays an essential role in the reduction 
of  environmental  and  social  risks,  including  human  rights  violations,  linked  to  the 
projects it finances and has therefore established its transparency policy, the purpose 
of which is to enhance the accountability of the Bank’s group towards its stakeholders 
and the citizens of the European Union in general.  
[…] 
 
NOW THEREFORE it is hereby agreed as follows:  
 
INTERPRETATION AND DEFINITIONS 
Interpretation 
In this Contract: 
[…] 
"Environment" means the following, in so far as they affect human health or social well-being:  
(a) 
fauna and flora;  
(b) 
soil, water, air, climate and the landscape; and  
(c) 
cultural heritage and the built environment, 
and includes, without limitation, occupational and community health and safety.  
"Environmental Approval" means any Authorisation required by Environmental Law. 
"Environmental Claim" means any claim, proceeding, formal notice or investigation by any 
person in respect of any Environmental Law.  
"Environmental Law" means:  
(a) 
EU Law, including principles and standards; 
(b) 
national laws and regulations; and 
(c) 
applicable international treaties, 
in each case of which a principal objective is the preservation, protection or improvement of 
the Environment. 
[…] 
ARTICLE 6 
Borrower undertakings and representations  
The undertakings in this Article 6 remain in force from the date of this Contract for so long as 
any amount is outstanding under this Contract or the Credit is in force. 
A.  PROJECT UNDERTAKINGS  
[…] 
6.5  
Continuing Project undertakings  
The Borrower shall:  
[…] 
 
 

 
 

 
(e) 
Environment:  
(i) 
implement and operate the Project in compliance with Environmental Law; 
(ii) 
obtain and maintain requisite Environmental Approvals for the Project; and  
(iii) 
comply with any such Environmental Approvals; and 
[…] 
6.18 
General Representations and Warranties 
The Borrower represents and warrants to the Bank that: 
[…] 
(o) 
it: 
[…] 
(i) 
to the best of its knowledge and belief (having made due and careful enquiry) no 
Environmental Claim has been commenced or is threatened against it: 
(1) 
that is not vexatious or frivolous; and 
(2) 
would  be  reasonably  likely,  if  adversely  determined,  to  have  a  material 
adverse effect on Borrower or the Project; and 
[…] 
 
ARTICLE 8 
Information and Visits 
8.1  Information concerning the Project  
The Borrower shall:     
(a) 
deliver to the Bank: 
(ii) 
[…]any  such  information  or  further  document  concerning  the  financing, 
procurement, implementation, operation and environmental matters of or for the 
Project as the Bank may reasonably require within a reasonable time,   
provided always that if such information or document is not  delivered to the  Bank on 
time, and the Borrower does not rectify the omission within a reasonable time set by the 
Bank  in  writing,  the  Bank  may  remedy  the  deficiency,  to  the  extent  feasible,  by 
employing  its  own  staff  or  a  consultant  or  any  other  third  party,  at  the  Borrower’s 
expense and the Borrower shall provide such persons with all assistance necessary for 
the purpose; 
[…] 
(b) 
promptly inform the Bank of: 
(i) 
any  action  or  protest  initiated  or  any  objection  raised  by  any  third  party  or  any 
genuine complaint received by the Borrower or any Environmental Claim that is 
to  its  knowledge  commenced,  pending  or  threatened  against  it  with  regard  to 
environmental or other matters affecting the Project; 
(ii) 
any  fact  or  event  known  to  the  Borrower,  which  may  substantially  prejudice  or 
affect the conditions of execution or operation of the Project;  
(iii) 
a genuine allegation, complaint or information with regard to Criminal Offences 
related to the Project;  
(iv) 
any non-compliance by it with any applicable Environmental Law; and 
 
 

 
 

 
(v) 
any suspension, revocation or modification of any Environmental Approval,  
and set out the action to be taken with respect to such matters; and 
[…] 
 
 
Schedule A 
 
Project Specification and Reporting 
[…] 
 
A.2  Information Duties under Article 8.1(a) 
[…] 
 
2.  Information on the project’s implementation  
 
The  Borrower  shall  deliver  to  the  Bank  the  following  information  on  project  progress  during 
implementation at the latest by the deadline indicated below. 
 
 
Document / information 
Deadline 
Frequency  of 
reporting 

 
[…] 
[…] 
Project Progress Report  
 
 
 
[…] 
 

A  description  of  any  major  issue  with  impact  on  the 
 
environment; 
 
[…] 
 
 
 
[…] 
 
3.  Information on the end of works and first year of operation  
 
 
The Borrower shall deliver to the Bank the following information on project completion and initial 
operation at the latest by the deadline indicated below. 
Document / information 
Date of delivery  
to the Bank 

Project Completion Report, including:  
[…] 
[…] 

A  description  of  any  major  issue  with  impact  on  the  environment  or 
social impacts; 

[…] 
 
[…]