Esta es la versión HTML de un fichero adjunto a una solicitud de acceso a la información 'Agreements and contracts with KIC InnoEnergy SE and its subsidaries'.








Amendment No. 1 of Specific Grant Agreement No. EIT/EIT INNOENERGY/SGA2020/1 
Ref. Ares(2020)3428534 - 30/06/2020
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
EIT – EIT InnoEnergy 
Specific Grant Agreement 2020 
 
 
 
 
 
 
Amendment No. 1 
 
 
 
Contract No. EIT/EIT INNOENERGY/SGA2020/1 
 
 
 

 





Amendment No. 1 of Specific Grant Agreement No. EIT/EIT INNOENERGY/SGA2020/1 
 
 
The  European  Institute  of  Innovation  and  Technology  ('the  EIT'),  represented  for  the  purposes  of 
signature of this Specific Agreement by its Director Martin KERN,  
 
and 
 
on the other part, 
 
1. The Knowledge and Innovation Community Legal Entity (hereinafter referred to as 'the KIC LE’): 
 
KIC  InnoEnergy  SE  (‘KIC  InnoEnergy’)  a  Societas  Europea  duly  incorporated  under  the  Laws  of  
The Netherlands with registered office located at the John F. Kennedylaan 2 6E Verdieping, 5612 AB 
Eindhoven,  the  Netherlands,  registered  in  the  Trade  Chamber  of  Eindhoven  under  the  number 
51418886,  represented  for  the  purpose  of  signing  the  Specific  Agreement  by  its  CEO  Diego  PAVIA, 
hereinafter referred to as the “KIC LE”, 
 
2.  and  the  other  Knowledge  and  Innovation  Community  ('KIC')  Partners  listed  in  Annex  2  of  the 
Framework  Partnership  Agreement,  represented  for  the  purposes  of  signing  the  Specific  Grant 
Agreement by the KIC LE (see the mandate in Annex 4 of the Framework Partnership Agreement and 
Article 62 of the Framework Partnership Agreement), 
Having regard to the Framework Partnership Agreement (Contract No. FPA2016/EIT/EIT InnoEnergy), 
concluded on 7 March 2016, hereinafter referred to as ‘FPA’, 
Having  regard  to  the  Specific  Grant  Agreement  2020  (Contract  No.  EIT/EIT  InnoEnergy/SGA2020) 
concluded between the EIT and the KIC LE on 20 February 2020, hereinafter referred to as ‘SGA2020’, 
Whereas,  
1)  On 20 February 2020 the SGA2020 was signed between the EIT and KIC LE, awarding the grant of 
EUR 81,785,400.38 representing the maximum EIT contribution. 
2)  Following  the  outbreak  of  the  COVID-19  pandemic,  on  14  May  2020  the  EIT  Governing  Board 
adopted its Decision 06/2020 and decided to allocate an additional amount of EUR 60,000,000 to 
the eight KICs for activities targeting the COVID-19 crisis and its negative economic effects.  
3)  Further to the EIT’s invitation to submit proposals for additional EIT funding in response to the 
COVID-19 crisis, the KIC submitted its proposal on 31 May 2020.  
4)  By its Decision 14/2020 the Governing Board decided on the maximum EIT financial contribution 
to  the  eight  KICs  for  activities  targeting  the  COVID-19  crisis.  The  EIT  Director  awarded  
EUR 7,388,122.27 for EIT InnoEnergy for these additional activities proposed by the KIC. 
5)  The  text  of  SGA2020  should  therefore  be  amended  accordingly;  the  corresponding  Annex  1 
(Description of the specific action) and Annex 2 (Estimated budget 2020) will be consolidated and 
amended by the upcoming Amendment No 2. 
 
 

 





Amendment No. 1 of Specific Grant Agreement No. EIT/EIT INNOENERGY/SGA2020/1 
 
 
HAVE AGREED AS FOLLOWS 
Article 1 
Article 4.2 of SGA2020 shall be replaced by the following:  
“4.2 
Maximum grant amount 
The 'maximum grant amount' is EUR 89,173,522.65 (eighty-nine million one hundred and seventy-three 
thousand five hundred and twenty-two euros and sixty-five eurocents), out of which: 

EUR 1,598,153.23 (one million five hundred ninety-eight thousand and one hundred fifty-three 
euros  and  twenty-three  cents)  shall  be  earmarked  for  the  implementation  of  the  Cross-KIC 
activities; and 

EUR 2,396,602.05 (two million three hundred ninety-six thousand and six hundred two euros 
and five cents) shall be earmarked for the implementation of EIT RIS activities.” 
Article 2 
Article 17.2 of the SGA2020 shall be replaced by the following: 
 
“The aim of the pre-financing is to provide the KIC Partners with a float. 
 
It remains the property of the EIT until the payment of the balance. 
 
The amount of the pre-financing payment will be EUR 62,421,465.86 (sixty-two million four hundred 
twenty-one thousand four hundred and sixty-five euros and eighty-six eurocents). 
 
The EIT will – except if Article 54 FPA applies – make the pre-financing payment to the KIC LE within 30 
days either from the entry into force of the Specific Agreement (see Article 21) or from 10 days before 
the starting date of the specific actions (see Article 3), whichever is the latest. 
 
An  amount  of  EUR  4,458,676.13  (four  million  four  hundred  fifty-eight  thousand  six  hundred  and 
seventy-six euros and thirteen eurocents), corresponding to 5.00% of the maximum grant amount (see 
Article 4.2), is retained by the EIT from the pre-financing payment and transferred into the 'Guarantee 
Fund'.” 
Article 3 
All other provisions of the SGA2020 shall remain unchanged and shall continue to apply. 
 
Article 4 
(1) The present amendment shall form an integral part of SGA2020 and it shall enter into force on the 
day of signature by the EIT or the KIC LE, depending on which is later.  

 





Amendment No. 1 of Specific Grant Agreement No. EIT/EIT INNOENERGY/SGA2020/1 
 
(2) The present amendment shall take effect on 1 April 2020.  
 
SIGNATURES 
 
 
For the EIT  
 
 
 
 
 
For the KIC LE 
Martin KERN, EIT Director 
 
 
 
Diego PAVIA, CEO 
 
 
 
 
 
 
Done in Budapest,                        2020 
 
 
Done in                    ,                             2020 
 
In duplicate, in English.