Ceci est une version HTML d'une pièce jointe de la demande d'accès à l'information 'Documents exchanged and presented within the framework of the Electricity Coordination Group (E02735).'.





Ref. Ares(2021)4296942 - 01/07/2021
TENERIFE BLACK-OUT   
July, 15th 2020 
Electricity Coordination Group  
September, 22th 2020 





Tenerife Characteristics 
 Isolated system (planned interconnection with La Gomera island) 
• Central dispatching model. 
• Low network mesh and concentrated generation (orography conditions).  
• Reserve levels (according to Operation Procedures): 97,98 MW to rump-up & 189 MW to rump-down.  
 
 
 Installed capacity (1225 MW) 
• Thermal capacity 918 MW: Granadilla (693 MW), Candelaria (139 MW), Arona (43MW), Guía de Isora (43MW).  
• Renewable capacity 307 MW: 196 MW (eolic) + 107 MW (photovoltaic) 
 




Black-Out Incident (1/3) 
 
 Before the incident 
• Demand: 
 
 
424 MW 
• Generation mix:    
15% RES (wind/solar)  
 
 
 
 
 
85% Thermal (steam/diesel/combined-cycle). 
 
• Granadilla Total Output: 
 
 
339 MW (94% demand) 

Granadilla CC-I: Gas 3 + Vapour 3:  
53,2 MW + 31,0 MW (84,2 MW) 

Granadilla CC-II: Gas 5 + Vapour 4:  
52,5 MW + 26,0 MW (78,5 MW) 
 
 Incident timeline 
• 09:41     Granadilla Gas 3 is accidentally manually triggered. Vapour 3 triggers. 
 
 
  
Frequency drops to 48,897 Hz. 
• +5,2s     Granadilla Gas 5 rumps-up to its maximum output, and trips due to high temperature gradient of  
   
 
exhaust gases. 
Frequency drops to 48,066 Hz  automatic under-frequency control scheme activates. 
• +2m5s    Granadilla Vapour 4 triggers . 
The performance of the automatic under-frequency control scheme was not enough to compensate the progressive 
generation loss. 
• 09:44  Frequency drops, all generation groups trigger, the black-out occurs.  
 
• Supply interruption:  
 
 
 
424 MW  
• Estimated Non Supplied Energy:    
1.913 MWh 
• Clients affected:   
 
 
 
over 515.000 




Black-Out Incident (2/3) 
 
 Incident timeline 
 
Generation and frequency variation during incident: 




Black-Out Incident (3/3) 
 
 Incident timeline 
 
Frequency variation during incident: 




Restoration Plan (1/2) 
 
 Tenerife system restoration plan 
1. Connection  of  power  sources  with  black  start  and  island  operation  capabilities:  Granadilla  & 
Candelaria gas turbines. 
2. Coupling of Granadilla & Candelaria gas turbines. 
3. Bottom-up demand re-energisation in a controlled and safe way. 
4. Supply re-energisation is completed at 16:44, once there is enough generation to supply all the 
demand. 
 
 Progressive generation coupling 




Restoration Plan (2/2) 
 
 Progressive supply re-energisation 
 

Time 
% Supply re-energised 
10:45 
4% (20.688 clients) 
11:30 
10 % (51.521 clients) 
12:30 
20 % (103.042 clients) 
13:20 
40 % (206.085 clients) 
14:40 
50 % (257.605 clients) 
15:15 
60 % (309.127 clients) 
15:40 
80 % (412.169 clients) 
16:45 
100 % (515.211 clients) 
Actual Supply vs Forecasted Supply 



Assesment and Conclusions (1/2) 
 
 On Wednesday, July 15th, 2020, Tenerife suffered an electrical blackout, starting at 09:41.  
All  substations  that  feed  the  distribution  network  had  tension  at  12:00,  and  full  supply  re-
energization occurred at 16:44. 
 
 Investigation and determination of liabilities on-going by regional authorities. 
 
 
 Difficulties 
• Tenerife is an isolated system, with low meshed grid. 
• Thermal generation is mainly concentrated in 2 sites. 
 
 
 Achievements 
• Effectiveness of Restoration Plan 
• Proper functioning of the control and command centers of the TSO & DSO. 




Assesment and Conclusions (2/2) 
 
 
 
 Conclusions 
 
• Interconnection  is  essential  to  ensure 
operational  security  and  to  facilitate  system 
restoration. 
 
• Grid  development  and  reinforcement  is  key  to 
achieve 

more 
meshed 
and 
robust 
transmission  system.  Storage  systems  would 
strengthen  the  transmission  system  and  the 
system  operation,  specially  regarding  RES 
i mplementation target (NECP 2030). 
 
• Improve reliability of generation groups, trying to avoid undesired triggers and to speed up black start processes.  
 
• TSO/DSOs should review, update & guarantee the proper implementation and function of the automatic under-
frequency control scheme and other emergency plans.  


Thank you for your attention