Standing Group on Electricity Scarcity 
Experiences & best practices of regional solidarity  
 
Electricity Coordination Group 
Brussels, 22/11/2019 
 

Background 



Recap of the situation 
 
 
 
 
 

For November 2018 only Doel 3 remained available, all other nuclear 
power plants would be off-line; 

Several measures at national level were taken to reduce the potential gap 
(e.g. re-entry into the market, revision of maintenance planning, 
emergency generators, DSM); 

Taking into account these measures, ELIA identified a remaining gap of 
700MW and 900MW, indicating structural imports would be needed
 
 
 

Standing Group & Operational Framework 


Standing Group on Electricity 
Scarcity 

In addition to bilateral consultations and ECG reporting, a Standing 
Group on Electricity Scarcity was created, in the context of the 
Pentalateral Energy Forum; 
 

Results initial assessment: 

Under normal winter conditions, sufficient production capacity would be 
available in the CWE-zone 

Doubts about the adequacy of transmission capacity to ensure the 
necessary imports to the Belgian market  
 

Conclusion of an “Operational framework for regional solidarity to 
ensure electricity adequacy in Belgium for the winter 2018-2019”  
 
 


Operational framework for 
regional solidarity
 

Applicable for winter 2018-2019 
 

Three key actions have been identified at regional level to mitigate 
potential electricity scarcity: 
 
1.
A  well-functioning  Flow-Based  market  coupling  at  the  Day-
Ahead time horizon in the CWE region 
 
- Ensure data quality 
 
- Apply seasonal thermal limits 
 
- Apply 20% MinRam 
 
- Ensure regional coordination to enable use of additional 
 
   PST-taps  
2.
An optimized intraday capacity calculation process 
3.
Coordinated Short and Medium Term Adequacy and Critical Grid 
Situation processes in place at Regional Security Centers (RSCs) 
 


Evaluation 
An auto-evaluation was performed by all MS after 
winter 2018-2019: 
 

The operational framework was vigorously applied 
 


Early regional consultation and cooperation in case of 
potential Critical Grid Situation  
 

Resulted in a problem-free winter 2018-2019 
 


Standing group seen as a valuable forum, which is added 
to the Penta-toolbox 
 


Remaining questions to be tackled in other fora, e.g. 
Pentalateral Energy Forum and Core. 
 
 
 

Conclusions 


Conclusions 

Regional solidarity works; 
 

Need for political impetus; 
 

Participation of MSs, NRAs and TSOs offers added 
value; 
 

Necessity of common vocabulary 
 

Building on existing cooperation mechanisms; 
 

Stepping stone for even stronger day-to-day 
cooperation; 
 

Useful tool in case of future emergencies.