Ref. Ares(2021)4296942 - 01/07/2021
ENTSO-E Transparency Platform
ECG web conference – 16 October 2020
Background
Freely
accessible
and
ENTSO-E to
downloadable
develop and
data
maintain the
Transparency
Platform (TP)
543/2013 EU
regulation
@ENTSO-E Al rights reserved
TP Regulation 543/2013 Article 15
Information relating to the unavailability of generation and production units
a) the planned unavailability of 100 MW or more of a generation unit including changes of 100 MW or more in the
planned unavailability of that generation unit, expected to last for at least one market time unit up to three years
ahead, specifying
b) changes of 100 MW or more in actual availability of a generation unit, expected to last for at least one market
time unit, specifying
• the name of the production unit,
• the name of the generation unit,
• location,
• bidding zone,
• installed generation capacity (MW),
• the production type,
• available capacity during the event,
• reason for the unavailability,
• start date and estimated end date (day, hour) of the change in availability
c) and d) tackle production units which are the collection of generation units and introduce a 200 MW threshold
@ENTSO-E Al rights reserved
TP data on planned and unplanned generation outages
Detailed description
Planned unavailability
• Data is to be published one hour after the decision is made
• Typically it is reported for future outages
Unplanned (forced) unavailability
• Data is to be published one hour after the decision is made in the changes of the availability of a unit
• Typically it is reported for an outage started in the past and finishes in the future.
This means planned unavailabilities that are already decided are published for the future on the TP.
Data quality and completeness is solely the responsibility of the owner of the data and the data
provider
ACER receives the data on a daily basis in the frame of the REMIT regulation
@ENTSO-E Al rights reserved
TP data
Overview
Time period filter
Control area filter
Data Export via
API or via xls
Timestamp (and
update history) is
available
@ENTSO-E Al rights reserved
TP data
Detailed view
Nature: planned/forced outage
Unit name included
Installed & available MW (hourly/15mins
resolution) during the outage
Production type: fuel type
@ENTSO-E Al rights reserved
@ENTSO-E Al rights reserved