This is an HTML version of an attachment to the Freedom of Information request 'Access to documents request: 2023-01-12 meeting between Stefano Grassi and Tatiana Marquez Uriarte and Enagás S.A.'.





Ref. Ares(2023)1307025 - 22/02/2023
  
 
 
BRIEFING FOR STEFANO GRASSI 
H2MED – MEETING WITH ENAGAS 
12 January 2023, Brussels 
 
SCENE SETTING 
 
The  project  H2Med  (formerly  called  ‘BarMar’)  is  an  interconnection  project  for  hydrogen 
infrastructure  between  Portugal,  Spain  and  France  submitted  for  PCI  status  by  4  different  gas 
transmission operators: Enagas (Spain), GRTgaz and Terega (France), REN (Portugal). The next list of 
PCIs is to enter into force in early 2024. 
It  was  agreed  at  the  level of  Leaders  in  the  presence  of  the  Commission  President  in  the  Alicante 
summit on 8/9 December 2022.  
The  project  includes  onshore  pipelines,  offshore  pipelines  and  compressor  stations.  The  project 
includes  2  cross-border  connections,  namely  Celorico-Zamora  (PT-ES)  and  Barcelona-Marseille  (ES-
FR).  
The main part of the project is a hydrogen interconnection project between Spain and France which 
will  be  ready  in  2030,  enabling  the  transport  of  2  Mt/y  of  H2  (i.e.  a  10%  of  the  expected  EU 
consumption  targets  by  2030:  20  Mt/y)  and  contributing  to  the  emergence  of  one  of  the  major 
import  corridors  via  the  Mediterranean  identified  in  the  REPowerEU  plan.  The  main  part  of  the 
project concerns a 455 km, 28 inch diameter offshore pipeline connecting Barcelona and Marseille, 
reaching a maximum depth of 2560 m.  
The  other interconnector is developed alongside  the interconnection between Portugal and Spain, 
consisting of a 248 km onshore pipeline (162 km in Portugal, 86 km in Spain) of 28’’ diameter as well 
as a compressor station in Zamora. The interconnection will have a capacity of 0.75 Mt/yr of H2.  
 
 

 
 
 
 

 

 
 
 
LTT 
 
Welcome words 
  The  REPowerEU  plan  to  provide  10  million  tonnes  of  domestic 
renewable hydrogen and 10 million tonnes of imported renewable 
hydrogen  will  require  infrastructure  to  bring  large  volumes  of 
hydrogen to the end-consumers. 
  This  will  require  several  hydrogen  corridors  from  the  South  of 
Europe towards demand centres and industrial clusters inland. 
  We  welcome  the  H2Med  as  it  has  the  potential  to  ensure  the 
crucial  connection  between  the  Iberian  Peninsula  and  France  for 
transporting  renewable  hydrogen  towards  North-Western  and 
Central Europe.  
  To be effective, the pipeline will need be complemented in time by 
a  hydrogen  grid  on  the  Iberian  Peninsula  and  by  a  South-North 
connection  in  France  and  further  on.  I  would  be  interested  in 
knowing  from  you  the  plans  of  Enagas  to  create  a  hydrogen 
backbone  in  Spain,  with  capacity  to  integrate  in  the  grid  and 
transport 2 Mt of hydrogen through Spain towards France.    
 
PCI and interconnection angle 
 
 

 

 
 
 
  H2Med and complementary projects have indeed been proposed 
as  part  of  the  on-going  selection  of  Projects  of  Common  Interest 
under the TEN-E Regulation.  
The Commission will work with Member States, Regulators and 
project promotors in regional groups to come up with the first list of 
Projects of Common and of Projects of Mutual Interest under the 
revised TEN-E Regulation by the 4th quarter of 2023 (entry into force 
in early 2024).On potential CEF funding 
  The  Connection  Europe  Facility  (CEF)  is  one  key  source  of  EU 
funding for energy infrastructure. In order to be eligible for a CEF 
grant,  the  H2Med  project  would  first  need  to  be  selected  as  a 
project of common interest (PCI) under the TEN-E Regulation. The 
first Union List of Projects of Common and of Mutual Interest will 
be final by early 2024. A CEF call for selected projects would follow 
in the course of 2024. 
  Moreover,  CEF  funding,  like  all  Union  funding,  for  PCIs  is  a  last 
resort.  The  CEF  budget  is  limited,  and  not  all  PCIs  receive  CEF 
funding. In fact, most PCIs should be commercially viable. The TEN-
E  Regulation  already  provides  other  advantages,  procedural  and 
regulatory, to PCIs. 
  CEF  grants  are  awarded  through  recurring  calls  for  proposals, 
where several PCIs compete for a limited call budget, meaning that 
not all proposals will be selected for funding. 
 
 

 

 
 
 
 
Hydrogen Bank 
  Another potential source of financing can come through the future 
European Hydrogen Bank, via support to hydrogen producers and 
consumers, who will in turn pay the transport fees of using the H2 
corridors.  
  The  key  objectives  of  the  European  Hydrogen  Bank  is  i)  to  cover 
the  cost  gap  between  renewable  and  fossil  hydrogen,  whilst 
leveraging a maximum amount of private financing into subsidized 
projects  and  ii)  to  contribute  to  early  market  formation  by 
providing price/cost discovery.  
  In  terms  of  scope,  the  Hydrogen  Bank  would  be  a  temporary 
mechanism  designed  to  complement  already  existing  public 
funding  resources  for  development  of  the  production,  use  and 
infrastructure of hydrogen at both EU and MS level. 
  The European Hydrogen Bank will be a financial policy instrument 
(not  as  a  physical  entity)  which  de-risks  and  creates  bankable 
hydrogen  projects,  ensures  competition  on  EU-level  and  avoids 
over-subsidizing projects; 
o  will  include  a  domestic  and  an  international  leg  of 
operations; 
 
 

 

 
 
 
o  Our  intention  is  to  develop  the  final  design  of  the 
Hydrogen  Bank  during  2023,  including  as  regards  the 
adoption of legal proposals. 
  While  the  Bank  will  initially  focus  on  supporting  domestic 
hydrogen  production,  our  REPowerEU  objectives  also  include  the 
import of 10 Mt/year of renewable hydrogen from Third countries 
by 2030. I understand that with its 2 Mt/year capacity (roughly 66 
TWh/y),  H2Med  will  still  have  some  capacity  left  (around  45 
TWh/y)  to  transport  H2  which  is  not  produced  in  the  Iberian 
Peninsula.  How  would  the  imported  H2  reach  the  Iberian 
Peninsula? Are there any plans of interconnections with the North 
of  Africa  or  are  these  volumes  expected  to  arrive  by  sea?  How 
feasible  would  the  scalability  of  the  H2Med,  should  additional 
domestic production or imports be available?         
 
 
 
 

 

 
 
 
Background 
Project outline 
The  project  H2Med  (formerly  called  ‘BarMar’)  is  an  interconnection  project  for  hydrogen 
infrastructure  between  Portugal,  Spain  and  France  submitted  for  PCI  status  by  4  different  gas 
transmission operators: Enagas (Spain), GRTgaz and Terega (France), REN (Portugal). It was agreed at 
the  level  of  Leaders  in  the  presence  of  the  Commission  President  in  the  Alicante  summit  on  8/9 
December 2022.  
The  project  includes  onshore  pipelines,  offshore  pipelines  and  compressor  stations.  The  project 
includes  2  cross-border  connections,  namely  Celorico-Zamora  (PT-ES)  and  Barcelona-Marseille  (ES-
FR).  
The main part of the project is a hydrogen interconnection project between Spain and France which 
will be ready in 2030, enabling the transport of 2 Mt/y of H2 and contributing to the emergence of 
one of the major import corridors via the Mediterranean identified in the REPowerEU plan. The main 
part of the project concerns a 455 km, 28 inch diameter offshore pipeline connecting Barcelona and 
Marseille, reaching a maximum depth of 2560 m.  
The  interconnector  is  developed  alongside  the  gas  interconnection  between  Portugal  and  Spain, 
consisting of a 248 km onshore pipeline (162 km in Portugal, 86 km in Spain) of 28’’ diameter as well 
as a compressor station in Zamora. The interconnection will have a capacity of 0.75 Mt/yr of H2.  
It is still unclear how the hydrogen will be transported inside the Spanish network (i.e. if and which 
ones sections of the Spanish gas network will be refurbished to become H2-dedicated pipelines) and 
similarly,  which  infrastructure  plans  have  GRTgaz  and  Terega  to  transport  the  hydrogen  as  from 
Marseille.  
Alternative routes 
There  is  no  other  comparable  South-North  corridor  connecting  the  Iberian  Penisula  with  North-
Western/Central  Europe.  We  received  PCI  applications  for  a  South-North  hydrogen 
corridor/backbone  within  Italy.  We  see  another  South-North  corridor  emerging  in  South-Eastern 
Europe,  albeit  much  smaller  in  capacity.  We  have  not  received  project  proposals  for  hydrogen 
interconnectors  from  Africa  as  part  of  the  on-going  PCI-PMI  selection,  although  according  to  the 
numbers presented by the three governments, the H2Med would have an excess of transportation 
capacity in 2030 (only 45 TWh/y of the 66 TWh/y capacity of the interconnector with France would 
be filled with H2 produced in the Iberian peninsula -see slide 4 in the PPT in annex, where 33 TWh 
represents 1 Mt of H2).    
The  preliminary  cost  estimation  of  the  project  is  around  2.5  billion  EUR.  The  project  is  in  pre-
feasibility  stage,  construction  should  start  in  2026,  and  the  focus  is  now  on  allocating  funding  for 
first phase studies (15 million EUR).  
Earlier competing project 
 
 

 


 
 
 
Before the announcement of the H2Med project, Snam and Enagas had signed a MoU aiming for a 
feasibility  study  on  a  sub-sea  pipeline  from  Barcelona  to  Tuscany  designed  to  transport  either 
natural gas or hydrogen. The pipeline capacity under assessment was in the range of 10-15bcm/year 
of natural gas. Our understanding from discussions with the operators is however that this project 
was abandoned/frozen, provided good progress with H2Med. 
H2 potential of the Iberian Peninsula 
The Commission is about to kick off a study to assess the H2 potential of the Iberian Peninsula and 
related infrastructure needs, steered by the High-Level Group Southwest Europe. 
Potential CEF funding 
If  the  Barmar  /  H2Med  project  is  included  in  the  list  of  projects  of  common  interest  (PCIs) 
established  under  the  TEN-E  Regulation, this would bring  a  series  of advantages:  First, the  project 
would  benefit  from  accelerated  authorisation  procedures  and  procedural  simplification  (notably  a 
one-stop  shop  in  the  Member  States  concerned).  Second,  depending  on  the  applicable  regulatory 
regime, it could also benefit from the regulatory tools that the TEN-E Regulation offers to facilitate 
the implementation of PCIs: the cross-border cost allocation procedure (to share construction costs 
among the relevant Member States according to the respective benefits the project procures them), 
or the granting of regulatory incentives by national regulatory authorities (NRAs). 
Third,  it  would  be  eligible  to  apply  for  EU  funding  under  the  Connecting  Europe  Facility  (CEF). 
However,  CEF  grants,  like  all  Union  grants,  are  a  “last  resort”  option  to  support  PCIs  after  other 
support  measures  provided  by  the  TEN-E  Regulation  have  been  exhausted.  Given  that  the  CEF 
budget is limited (EUR 5.8 billion over the whole MFF period 2021-2027, of which approx. EUR 1.6 
billion have already been committed to other projects), only a small number of PCIs will therefore 
receive funding, and only after applying for a CEF call where their proposals will be competing with 
funding  proposals  from  other  PCIs  for  a  call  budget  that  is  lower  than  the  sum  of  all  grants 
requested. 
Among the highest CEF grants awarded for PCIs so far, there are the following (with the year of the 
call in brackets): a total of EUR 1.2 billion for the synchronisation of the Baltic States (several calls); 
EUR 579 million for the French-Spanish electricity interconnector Biscay Bay (2017); EUR 531 million 
for  the  French-Irish  electricity  interconnector  Celtic  (2019);  EUR 656  million  for  the  Cypriot-Greek 
electricity interconnector EuroAsia (2021). 
Attachment: PowerPoint on H2Med used for the Alicante Summit at Leaders’ level, 8/9 December 
2022  

20221130H2MED_E
N_v10.pptx