This is an HTML version of an attachment to the Freedom of Information request 'Overview about energy infrastructure projects funded by EU'.


  
 
EUROPEAN 
  COMMISSION 
 
Brussels, 5.3.2018  
COM(2018) 86 final 
 
REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN 
PARLIAMENT 
On the implementation of the European Energy Programme for Recovery and the 
European Energy Efficiency Fund 
{SWD(2018) 48 final} 
 
EN 
 
  EN 

 
REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND 
THE COUNCIL 
On the implementation of the European Energy Programme for Recovery  
and the European Energy Efficiency Fund 
A  resilient  infrastructure  is  the  backbone  of  the  Energy  Union.  Last  year,  important 
interconnection  projects  were  put  in  operation  and  regional  cooperation  was  considerably 
strengthened
In that context the EEPR played a key role in the financial support to major infrastructures of 
common interest for the integration of the electricity and gas markets and the reinforcement of 
the security of supply. 
I.  PROGRESS IN PROGRAMME IMPLEMENTATION 
Energy  infrastructure  and  innovation,  the  driving  forces  behind  the  European  Energy 
Programme  for  Recovery  (EEPR),  remain  as  important  now  as  they  were  in  2009  when  the 
EEPR was set up.  
This  report  sets  out,  for  each  part  of  the  EEPR,  the  progress  made  in  implementing  the 
projects  and  the  European  Energy  Efficiency  Fund  (EEEF).  It  follows  the  report  adopted  in 
20161. It covers the implementation of the projects between 31 August 2016 and 30 June 2017 
and the payments made during that period. 
 
II. OVERALL PROJECT IMPLEMENTATION  
By the end of June 2017, 37 projects out of 59 have been completed and a total amount of € 
2,279,701,215  (after  deduction  of  the  recovery  orders  for  an  amount  of  €  159,202,466)  has 
been paid to the beneficiaries. 
The situation for the gas and electricty infrastructures is as follows : five projects are on track 
with one currently being under discussion. Most of the projects are completed and promoters 
are expected to present the final payment request by the end of this year. 
Substantial  progress  was  made  by  the  promoters  for  the  Off-Shore  Wind  Energy  (OWE) 
integration in the grid whilst the project promoters of the last remaining CCS project decided 
to stop their financial support to the project. 
The Commission has opted for maintaining its financial support to the investors as long as it 
remains clear that a Final Investment Decision (FID) is possible. 
1. 
GAS AND ELECTRICITY INFRASTRUCTURE   
The  EEPR  infrastructure  sub-programme  has  supported  44  projects  in  three  major  areas  of 
activities.  
                                                            
1 Report 2016 adopted on , 28.11.2016 COM(2016) 743 final 

 

 
A total amount of € 2,267,574,462 has been committed, of which € 1,483,712,280 has been 
disbursed to the beneficiaries by 30 June 2017. Payments are subject to the beneficiaries' firm 
commitment to implement the project through a Final Investment Decision.  
1.1.PROGRESS TO DATE  
To  date,  35  out  of  the  44  infrastructure  projects  have  been  completed,  four  projects  are  on-
going and one is in under discussion.  
In the electricity sector, 10 out of 12 projects have been completed. The 2 remaining projects 
are progressing well and are expected to be completed by the end 2017.  
In the gas sector, 25 out of 32 projects have been completed; two are progressing according to 
schedule, one is currently under discussion and four have been terminated. All of the reverse 
flow  and  interconnections  projects  in  Central  and  Eastern  Europe  have  been  completed, 
except  the  reverse  flow  project  in  Romania  that  was  terminated  by  the  Commission  in 
September 2014.  
Important progress has been made for electricity and gas infrastructure projects since the last 
2016 EEPR implementation report.  
For instance, the reinforcement of French gas network on the Africa-Spain-France axis is on 
track.  The  project  will  develop  the  gas  network  in  France  in  order  to  reinforce  the  Africa-
Spain-France  axis  (Saint-martin  de  Crau-Saint  Avit  and  Lacal-Lussagnet).  The  project  will 
increase  security  of  supply  and  market  competition  in  the  region.  The  EEPR  funds  have 
secured  the  development  of  the  project  notably  on  the  Eastern  axis  by  encouraging  the 
beneficiaries to take their investment decision. 
The Bulgarian – Romanian interconnection has been implemented successfully end 2016. The 
completion  of  this  project  allows  a  better  integration  of  the  gas  market  in  the  region  and 
increase the Bulgarian security of supply, as well as support the opening of the Southern Gas 
Corridor. 
The  electricity  project  Halle/Saale  –  Schweinfurt  links  the  North-Eastern  part  to  the  South-
Eastern  part  of  Germany  facilitating  the  transport  of  electricity  from  renewable  energy 
sources  produced  in  North  Germany  and  in  the  North  Sea  region  to  the  rest  of  the  German 
grid. The interconnector was completed end of September 2017. 
The  Nordbalt  1  project  consisted  of  the  construction  of  the  Swedish  -  Lithuanian  electricity 
transmission systems' interconnection by a High Voltage Direct Current (HVDC) submarine 
cable  with  a  capacity  of  700  MW.  The  project  aims  at  further  removing  the  Baltic  States 
isolation from the internal energy market. All works have been completed.  
To date, it is foreseen that out of the 5 on-going projects, 3 should be completed in 2017, with 
1 in 2018 and one under discussion. 
2. OFFSHORE WIND ENERGY (OWE) PROJECTS 
2.1 PROGRESS TO DATE  
The  Offshore  Wind  sub-programme  consisted  of  9  projects  giving  €  565  million  of  support 
split between two main types of activities: 
  Large-scale  testing,  manufacturing  and  deployment  of  innovative  turbines  and  offshore 
foundation structures (6 projects); and 

 

 
  Development of module-based solutions for the grid integration of large amounts of wind 
electricity transmission (3 projects). 
4  of  9  projects  have  been  completed  and  2  terminated  prematurely.  €  255,744,668  (after 
deduction of recovery orders) has been paid to the projects. The three remaining projects are 
on-going . 
2.2 PROGRESS TO DATE BY SECTOR  
2.2.1 Progress with Innovative Turbines and Offshore Structures 
For  Aberdeen  Offshore  Wind  Farm,  a  positive  FID  was  taken  in  July  2016.  The  challenges 
related  to  obtain  both  the  offshore  and  onshore  consents  have  delayed  the  project  and  the 
estimate  for  the  construction  commencement  is  now  the  fourth  quarter  of  2017  (with 
commissioning mid 2019). 
The Noordsee Oost Offshore Wind Farm project was successfully completed in May 2016. 
The Global Tech I project did not find a co-investor. Therefore the Commission confirmed in 
April 2015 the project termination retroactively as of 1 January 2014.  
2.2.2 Progress with Wind-Grid Integration 
One project, HVDC Hub, has been terminated.  
In  general  the  execution  of  the  two  remaining  projects,  Kriegers  Flak  and  Cobra  Cable, 
progressed as  expected. For  Kriegers  Flak, in  September 2015, the amendment of the Grant 
Agreement  for  the  new  technical  solution  was  approved  by  European  Commission.  The 
beneficiaries 50Hertz and Energinet.dk have made the Final Construction Decision (FCD). 
The EU tendering for main equipment to the infrastructure is close to be finalized. According 
to the plan, beneficiaries have awarded nearly all contracts and the construction is in progress. 
The  permission  process  for  Germany  and  Denmark  is  progressing  as  foreseen.The  offshore 
interconnector Kriegers Flak CGS is planned to be commissioned by end of 2018.  
For  Cobra  Cable,  following  the  Final  Investment  Decision  taken  in  December  2015,  the 
project is on track for many of the deliverables except for two, namely the production and test 
of  the  converters  and  the  cable.  Therefore,  a  12  months  extension  of  the  contract  will  be 
needed to maintain the finalisation of the activities and submission of the deliverables within 
the contract duration. The construction and testing of the interconnector is scheduled for 2018 
in  order to  start operation in  2019. The high  level study is on-going  and aims at identifying 
and describing the important design issues to be taken into account to make the HVDC link 
prepared for future operation as part of multi-terminal network. 
3. CARBON CAPTURE AND STORAGE 
The  EEPR  sub-programme  consisted  of  6  projects  and  €  1  billion  of  support  aiming  at 
demonstrating the full carbon capture, transport and storage process.  
One project was finished providing operational pilot plants for capture, transport and storage. 
Three projects have been terminated prematurely due to the decision of the project promoter 
not  to  invest,  one  project  ended  without  completion  and  ROAD  was  the  last  remaining 
project. € 424,040,501 has been paid to these projects.  
Progress with CCS projects 

 

 
In November 2016 the Commission and the ROAD project promoters agreed an extension of 
the grant agreement until 31 December 2019 following progress in discussions on additional 
sources  of  funding,  restructuring  of  the  project  and  change  to  a  less  costly  storage  site. 
However, in June 2017 the project promoters informed the Commission that the joint venture 
partners Engie and Uniper decided to stop their financial support for the project and later on 
confirmed  that  they  withdraw  the  request  for  the  grant  agreement.  Consequently  the  grant 
agreement is in the process of being terminated. Nevertheless, a new project is in preparation 
under the leadership of the Port of Rotterdam that could possibly use other Community funds, 
if successful.  
III. EUROPEAN ENERGY EFFICIENCY FUND (EEEF)  
In  December  2010,  €  146.3  million  from  the  European  Energy  Programme  for  Recovery 
(EEPR)  were  allocated  to  a  financial  facility  for  sustainable  energy  projects2.  €  125  million 
were used as the EU contribution to the European Energy Efficiency Fund (EEEF), created in 
July 2011 and which has reached a total volume of € 265 million3, supported by a Technical 
Assistance grant facility with a budget of € 20 million and € 1.3 million for awareness-raising 
activities. 
The  EEEF  provides  tailored  financing  (both  debt  and  equity  instruments)  for  energy 
efficiency,  renewable  energy  and  clean  urban  transport  projects.  Beneficiaries  are  local  or 
regional public authorities or private entities acting on their behalf. 
 
PROGRESS TO DATE 
In  2016,  a  new  transaction  was  added  to  the  Fund’s  portfolio.  Ore  Valley  Housing 
Association (OVHA) has reached financial close with EEEF on a project worth £4.6 million. 
The  money  will  fund  the  development  of  wind  turbine  sites  in  Fife-Scotland,  plus  an 
innovative  funding  scheme  replacing  200  heating  systems  for  OVHA  homes.  This  was 
EEEF’s first community based transaction within the UK, and is the result of a four-year long 
co-operative effort between EEEF and OVHA.  
From its creation to 31st December 2016, the EEEF has signed contracts with 11 projects for 
€121 million, which have generated €224 million of final investments.  
Based  on  the  EEEF's  project  assessment  and  reporting  framework  on  CO2  equivalent  and 
primary energy savings, as of the end of 2016, its investments have achieved savings of close 
to 249 000 tons of CO2 and Primary Energy Savings4 of 308 802 MWh. 
 
European Commission Technical Assistance facility 
                                                            
2  
Regulation (EU) No 1233/2010 of the European Parliament and of the Council of 15 December 2010 
amending  Regulation  (EC)  NO  663/2009  establishing  a  programme  to  aid  economic  recovery  by  granting 
Community financial assistance to projects in the field of energy. 
3  
Additional  investments  to  those  of  the  European  Commission  have  been  made  by:  the  European 
Investment  Bank  EUR  75  million,  Cassa  Depositi  e  Prestiti  SpA  (CDP)  EUR  60  million  and  the  Investment 
Manager Deutsche Bank (DB) EUR 5 million. 
4  Cumulative  primary  energy  savings  are  presented  only  for  Energy  Efficiency  and  Clean  Urban  Transport 
technologies; they include calculations from financial close to loan maturity, based on estimations for projects 
under  construction  and  less  than  one  year  of  operations  and  actual  data  for  projects  which  have  been  in 
operation  for  over  one  year.  Savings  are  for  total  project  investment  volume  (i.e.  EEEF  and  non-EEEF 
investments). 

 

 
In 2016, no additional funds were allocated to finance project development activities.  
In total, the Technical Assistance facility funded by the Commission will have supported the 
structuring of 16 projects for a total allocated amount of € 16 million (out of the €20 million 
budget). Several factors can explain the reasons for the unallocated funds. First, the projects 
identified  in  the  ramp-up  phase  of  the  Fund  had  a  higher  advancement  stage/maturity  level 
and  therefore  did  not  need  technical  assistance.  Moreover,  the  experience  of  the  Technical 
assistance facility has shown that financing energy efficiency projects faces many challenges, 
such as a lower level of preparation of requests than initially estimated at the inception of the 
EEEF (few of the technical assistance requests received were ready for submission), changes 
in projects following political changes in governments, or necessary adaptations after the first 
set of feasibility studies. 
EEEF Technical Assistance facility  
In  November  2016,  the  European  Energy  Efficiency  Fund  launched  a  new  facility  for 
Technical  Assistance  (TA).  Following  on  from  the  European  Commission’s  TA  facility, 
managed by EEEF, the Fund has set up a new tool to support ambitious public beneficiaries 
with bankable sustainable energy investment projects. Such projects shall relate to the energy 
efficiency  sector,  small-scale  renewable  energy  and/or  public  transport  initiatives.  EEEF  is 
supporting  beneficiaries  –  regions,  city  councils,  universities,  public  hospitals  and  other 
public  entities  located  in  the  28  EU  Member  States  –  by  way  of  allocating  consultancy 
services to the planned investments, for instance performing feasibility studies, energy audits, 
legal  services  and  analysis  of  economic  viability.  EEEF  TA  Facility  has  received  funding 
from the ELENA facility under the Horizon 2020 Programme of the European Union. 
Main Conclusions & outlook 
The EEEF has progressively established a solid track record of profitable investments and will 
actively look for additional senior investors to leverage the EU contribution further. 
For 2017, the project pipeline contains 17 projects with a total volume of EUR 337 million for 
which  the  envisaged  EEEF  share  is  EUR  142  million.  The  EEEF  will  continue  to  seek  to 
broaden its geographical coverage, where project and market conditions permit. 
 
IV. OVERALL CONCLUSIONS 
The  EEPR  has  delivered  good  results.  The  majority  of  projects  have  been  completed, 
particularly  regarding  gas  and  electricity  infrastructures.  The  strict  control  exercised  by  the 
European  Commission  in  project  implementation  and  monitoring  has  helped  to  increase  the 
efficiency of the instrument. 
Despite the fact that Off-Shore Wind projects appeared to be more complex than expected, the 
promoters  and  the  constructors  have  managed  to  find  solutions  and  the  technological 
knowledge has been gained over the five years.  
Although  the  financial  support  of  EEPR  was  not  sufficient  to  prompt  companies  to  realise 
commercial-scale CCS demonstration projects, the Commission still considers CCS important 
for  decarbonisation.  Future  CCS  demonstration  efforts  in  Europe  are  expected  to  focus  on 
energy- and carbon intensive industries. 
The  EEEF  invested  in  several  energy  efficiency  projects  and  will  continue  to  expand  its 
portfolio,  providing  financing  solutions  and  generating  profits  covering  administrative 

 

 
expenses, shareholders’ dividend and repayment of establishment costs. The EEEF also serves 
as  a  role  model  for  innovative  financial  instruments  investing  in  cost-effective  and  mature 
sustainable  energy  projects  (with  payback  periods  of  up  to  18  years)  that  can  attract  private 
capital  while  demonstrating  the  business  case  behind  these  investments  and  creating  a 
credible track record. 

 

Document Outline